Granite Remedial Work
Atlanta, Georgia

Service provided: Project Management, 06/97 - 07/98

Client: Raymond James Realty Advisors

Owner: Northpark Associates

Contractor: Crystal Marble

Project Budget : $1M - $5M

The NPTC Building 400 tower, bridge & garden building was faced with granite tiles which had been adhered to the concrete structure using only mortar. Some granite tile had become loose. CRESG worked with the contractor to develop a method for mechanically fastening the tiles. CRESG served as the project manager for the remedial work involving pinning tiles to the structure.

 